Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-161-10-28 12-0C3504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-39-0.0/21.9 Federal Project: NONE Progress payment No. 09 Payment period ending: 05-05-09 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 684,178.45 2,015.50 2.a. Extra Work 77,286.67 10,344.68 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 761,465.12 12,360.18 5. Mobilization 57,000.00 0.00 6. Total Work Completed 818,465.12 7. Deductions 8. a.Contract Retentions -35,454.36 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 35,454.36 0.00 9. Total pay to Contractor 818,465.12 12,360.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,360.18