Dept. of Trans. PROGRESS Serial No. Contract No. 04-355-14-48 12-0C98C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 53% 12-ORA-73-23.6/23.6 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-04 P P C CONSTRUCTION INC 336 N CENTRAL AVENUE SUITE 10 GLENDALE CA 91203 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 137,270.00 120,770.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 137,270.00 120,770.00 5. Mobilization 36,100.00 36,100.00 6. Total Work Completed 173,370.00 7. Deductions -1,155.00 0.00 8. a.Contract Retentions -9,001.36 -7,351.36 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 163,213.64 149,518.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 149,518.64