Dept. of Trans. PROGRESS Serial No. Contract No. 10-168-08-51 12-0E0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-5-15.1/16.4 Federal Project: NONE Progress payment No. 23 Payment period ending: 06-20-10 ORTIZ ENTERPRISES INCORPORATED 6 CUSHING SUITE 200 IRVINE CA 92618 Escrow No. 02398 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,265,243.96 822,996.38 2.a. Extra Work 431,218.25 4,339.04 b. Adjustment Comp. -239,858.51 -261,219.80 3. Materials on Hand 198,283.92 -44,812.09 4. Earned Subject to Retention 10,654,887.62 521,303.53 5. Mobilization 1,260,000.00 0.00 6. Total Work Completed 11,716,603.70 7. Deductions -1,102.50 0.00 8. a.Contract Retentions -532,744.38 -26,065.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,381,040.74 495,238.35 10. Reduction Amt to Escrow 11. Payment to Escrow 532,740.00 12. Net Pymt. this Estimate 495,238.35