Dept. of Trans. PROGRESS Serial No. Contract No. 11-034-11-00 12-0E0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-5-15.1/16.4 Federal Project: NONE Progress payment No. 30 Payment period ending: 01-20-11 ORTIZ ENTERPRISES INCORPORATED 6 CUSHING SUITE 200 IRVINE CA 92618 Escrow No. 02398 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,456,867.66 18,580.00 2.a. Extra Work 491,415.43 7,499.91 b. Adjustment Comp. -172,898.51 0.00 3. Materials on Hand 198,283.92 0.00 4. Earned Subject to Retention 10,973,668.50 26,079.91 5. Mobilization 1,260,000.00 0.00 6. Total Work Completed 12,035,384.58 7. Deductions -11,102.50 -10,000.00 8. a.Contract Retentions -548,683.43 -1,304.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,673,882.57 14,775.91 10. Reduction Amt to Escrow 11. Payment to Escrow 548,680.00 12. Net Pymt. this Estimate 14,775.91