Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-052-08-10 12-0E0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-5-15.1/16.4 Federal Project: NONE Progress payment No. 41 Payment period ending: 09-19-11 ORTIZ ENTERPRISES INCORPORATED 6 CUSHING SUITE 200 IRVINE CA 92618 Escrow No. 02398 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,644,906.70 7,355.83 2.a. Extra Work 890,759.11 16,885.75 b. Adjustment Comp. 875,899.81 60,645.96 3. Materials on Hand 4. Earned Subject to Retention 13,411,565.62 84,887.54 5. Mobilization 1,260,000.00 0.00 6. Total Work Completed 14,671,565.62 7. Deductions -1,102.50 0.00 8. a.Contract Retentions -645,467.95 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 645,467.95 0.00 9. Total pay to Contractor 14,670,463.12 84,887.54 10. Reduction Amt to Escrow -645,460.00 0.00 11. Payment to Escrow 645,460.00 12. Net Pymt. this Estimate 84,887.54