Dept. of Trans. PROGRESS Serial No. Contract No. 07-025-12-58 12-0E1604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 11% 12-ORA-0 Federal Project: ACST-X059(46) PHG-X059(46) Progress payment No. 01 Payment period ending: 01-20-07 T D S ENGINEERING 2899 AGOURA ROAD STE 171 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 181,592.00 181,592.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 181,592.00 181,592.00 5. Mobilization 120,000.00 120,000.00 6. Total Work Completed 301,592.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 301,592.00 301,592.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 301,592.00