Dept. of Trans. PROGRESS Serial No. Contract No. 16-118-08-16 12-0E3104 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 80% Location: Federal Project: 12-ORA-74-0.0/0.2 NONE Progress payment No. 040 Payment period ending: 04-20-16 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,213,887.72 9,343.75 2. a. Extra Work 612,013.55 125,056.39 b. Adustment Comp. 322,084.41 0.00 3. Materials on Hand 4. Earned Subject to Retention 23,147,985.68 134,400.14 5. Mobilization 1,600,000.00 0.00 6. Total Work Completed 24,747,985.68 7. Deductions -54,900.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,693,085.68 134,400.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 134,400.14