Dept. of Trans. PROGRESS Serial No. Contract No. 16-083-09-31 12-0E31A4 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 8% Location: Federal Project: 12-ORA-74-0.0/1.6 NHP-IMP X059-062-E Progress payment No. 002 Payment period ending: 03-20-16 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 93,039.75 8,935.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 93,039.75 8,935.00 5. Mobilization 52,500.00 0.00 6. Total Work Completed 145,539.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 145,539.75 8,935.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,935.00