Dept. of Trans. SEMI-FINAL Serial No. Contract No. 19-282-08-00 12-0E31A4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-74-0.0/1.6 NHP-IMP X059-062-E Progress payment No. 045 Payment period ending: 08-29-19 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 751,627.00 10,476.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 751,627.00 10,476.25 5. Mobilization 70,000.00 0.00 6. Total Work Completed 821,627.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 821,627.00 10,476.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,476.25