Dept. of Trans. PROGRESS Serial No. Contract No. 07-170-08-22 12-0E7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 43% 12-ORA-5-3.6/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-07 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02277 Total Estimate This Estimate 1. Contract Itms Without Mobil. 549,066.50 378,862.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 549,066.50 378,862.00 5. Mobilization 307,500.00 307,500.00 6. Total Work Completed 856,566.50 7. Deductions 8. a.Contract Retentions -54,906.65 -37,886.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 801,659.85 648,475.80 10. Reduction Amt to Escrow 11. Payment to Escrow 54,900.00 12. Net Pymt. this Estimate 648,475.80