Dept. of Trans. PROGRESS Serial No. Contract No. 08-172-08-57 12-0E7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-5-3.6/ .0 Federal Project: NONE Progress payment No. 15 Payment period ending: 06-20-08 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331-0189 Escrow No. 02277 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,816,081.13 3,598.30 2.a. Extra Work 56,489.69 805.79 b. Adjustment Comp. 15,206.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,887,776.82 4,404.09 5. Mobilization 410,000.00 0.00 6. Total Work Completed 4,297,776.82 7. Deductions 8. a.Contract Retentions -194,388.84 -220.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,103,387.98 4,183.89 10. Reduction Amt to Escrow 11. Payment to Escrow 194,160.00 12. Net Pymt. this Estimate 4,183.89