Dept. of Trans. PROGRESS Serial No. Contract No. 13-325-10-00 12-0F0314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 88% 12-ORA-57-16.2/18.8 Federal Project: NONE Progress payment No. 38 Payment period ending: 11-20-13 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,353,407.94 828,566.80 2.a. Extra Work 521,415.21 7,780.54 b. Adjustment Comp. 111,898.96 0.00 3. Materials on Hand 195,229.91 -90,674.09 4. Earned Subject to Retention 24,181,952.02 745,673.25 5. Mobilization 1,177,219.50 0.00 6. Total Work Completed 25,163,941.61 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,354,171.52 745,673.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 745,673.25