Dept. of Trans. PROGRESS Serial No. Contract No. 18-296-10-54 12-0F03U4 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 47% Location: Federal Project: 12-ORA-57-16.2/20.9 NONE Progress payment No. 006 Payment period ending: 10-20-18 ACCU CONSTRUCTION INC 2098 S GRAND AVE #A SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 521,849.60 193,023.30 2. a. Extra Work 20,847.49 3,900.22 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 542,697.09 196,923.52 5. Mobilization 9,500.00 0.00 6. Total Work Completed 552,197.09 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 552,197.09 196,923.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 196,923.52