Dept. of Trans. PROGRESS Serial No. Contract No. 14-296-09-26 12-0F0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 12-ORA-57-12.3/15.2 Federal Project: NONE Progress payment No. 38 Payment period ending: 10-20-14 C. C. MYERS, INC. PO BOX 2948 RANCHO CORDOVA CA 95741-2948 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,108,345.88 1,037,872.26 2.a. Extra Work 702,658.19 16,490.00 b. Adjustment Comp. 621,936.00 38,375.00 3. Materials on Hand 48,136.76 -57,430.37 4. Earned Subject to Retention 16,481,076.83 1,035,306.89 5. Mobilization 1,390,000.00 0.00 6. Total Work Completed 17,822,940.07 7. Deductions -49,580.00 -560.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,821,496.83 1,034,746.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,034,746.89