Dept. of Trans. PROGRESS Serial No. Contract No. 05-083-16-21 12-0F5704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 7% 12-ORA-91-9.0/10.1 Federal Project: NONE Progress payment No. 01 Payment period ending: 03-20-05 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 70,360.00 70,360.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 41,110.20 41,110.20 4. Earned Subject to Retention 111,470.20 111,470.20 5. Mobilization 102,409.50 102,409.50 6. Total Work Completed 172,769.50 7. Deductions 8. a.Contract Retentions -11,147.02 -11,147.02 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 202,732.68 202,732.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,732.68