Dept. of Trans. PROGRESS Serial No. Contract No. 04-111-15-26 12-0F6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 24% 12-ORA-57-19.7/19.7 Federal Project: ACST-P057(45) PH-P057(45) Progress payment No. 02 Payment period ending: 04-20-04 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 129,932.23 67,101.88 2.a. Extra Work 850.00 850.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 130,782.23 67,951.88 5. Mobilization 53,200.00 11,200.00 6. Total Work Completed 183,982.23 7. Deductions -9,312.09 -1,960.44 8. a.Contract Retentions -8,336.56 -2,053.52 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 166,333.58 75,137.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 75,137.92