Dept. of Trans. PROGRESS Serial No. Contract No. 09-083-12-26 12-0F8204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 100% 12-ORA-5-13.8/13.8 Federal Project: NONE Progress payment No. 10 Payment period ending: 03-20-09 O DONNELL CONSTRUCTION INC 559 WEST COVINA BOULEVARD SAN DIMAS CA 917732911 Escrow No. 02365 Total Estimate This Estimate 1. Contract Itms Without Mobil. 718,897.20 48,382.00 2.a. Extra Work 9,392.55 0.00 b. Adjustment Comp. 1,199.51 0.00 3. Materials on Hand 4. Earned Subject to Retention 729,489.26 48,382.00 5. Mobilization 85,500.00 0.00 6. Total Work Completed 814,989.26 7. Deductions 8. a.Contract Retentions -36,474.46 -2,419.10 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 778,514.80 45,962.90 10. Reduction Amt to Escrow 11. Payment to Escrow 36,470.00 12. Net Pymt. this Estimate 45,962.90