Dept. of Trans. FINAL Serial No. Contract No. 09-286-09-25 12-0F8204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-5-13.8/13.8 Federal Project: NONE Progress payment No. 17 Payment period ending: 07-24-09 O DONNELL CONSTRUCTION INC 559 WEST COVINA BOULEVARD SAN DIMAS CA 917732911 Escrow No. 02365 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,473,847.69 0.00 2.a. Extra Work 49,504.39 0.00 b. Adjustment Comp. 6,291.97 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,529,644.05 0.00 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,619,644.05 7. Deductions -5,000.00 0.00 8. a.Contract Retentions -75,945.11 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 75,945.11 0.00 9. Total pay to Contractor 1,614,644.05 0.00 10. Reduction Amt to Escrow -75,940.00 0.00 11. Payment to Escrow 75,940.00 12. Net Pymt. this Estimate 0.00