Dept. of Trans. PROGRESS Serial No. Contract No. 10-055-13-40 12-0F9004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 32% 12-ORA-405-0.2/24.2 Federal Project: NONE Progress payment No. 01 Payment period ending: 02-20-10 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 927111238 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 59,022.50 59,022.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 59,022.50 59,022.50 5. Mobilization 30,400.00 30,400.00 6. Total Work Completed 89,422.50 7. Deductions -12,393.05 -12,393.05 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 77,029.45 77,029.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,029.45