Dept. of Trans. PROGRESS Serial No. Contract No. 11-173-07-17 12-0F9204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 70% 12-ORA-5-6.0/31.2 Federal Project: ACIM-005-2(944) Progress payment No. 05 Payment period ending: 06-20-11 Y A K A R 113 E ARROW HIGHWAY SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 373,978.65 230,710.75 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 373,978.65 230,710.75 5. Mobilization 70,300.00 33,300.00 6. Total Work Completed 444,278.65 7. Deductions 0.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 444,278.65 269,010.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 269,010.75