Dept. of Trans. PROGRESS Serial No. Contract No. 11-208-13-23 12-0F9204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 79% 12-ORA-5-6.0/31.2 Federal Project: ACIM-005-2(944) Progress payment No. 06 Payment period ending: 07-20-11 Y A K A R 113 E ARROW HIGHWAY SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 724,008.15 350,029.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 724,008.15 350,029.50 5. Mobilization 70,300.00 0.00 6. Total Work Completed 794,308.15 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 794,308.15 350,029.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 350,029.50