Dept. of Trans. PROGRESS Serial No. Contract No. 12-265-08-55 12-0F9204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP UNSAT 12-ORA-5-6.0/31.2 Federal Project: ACIM-005-2(944) Progress payment No. 20 Payment period ending: 09-20-12 Y A K A R 113 E ARROW HIGHWAY SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,588,220.75 -6,750.00 2.a. Extra Work 57,070.00 11,314.67 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,645,290.75 4,564.67 5. Mobilization 74,000.00 0.00 6. Total Work Completed 1,719,290.75 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. -456.47 -456.47 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,717,834.28 4,108.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,108.20