Dept. of Trans. PROGRESS Serial No. Contract No. 16-265-09-26 12-0F96A4 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 39% Location: Federal Project: 12-ORA-5-3.0/3.7 NHPI-005-2(972) PLN-6212(16) Progress payment No. 020 Payment period ending: 09-20-16 FLATIRON WEST INC. 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,978,100.24 1,443,805.07 2. a. Extra Work 384,870.40 40,928.69 b. Adustment Comp. 181,076.68 0.00 3. Materials on Hand 473,271.47 -56,961.24 4. Earned Subject to Retention 24,017,318.79 1,427,772.52 5. Mobilization 4,123,000.00 0.00 6. Total Work Completed 27,667,047.32 7. Deductions -10,839.97 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,129,478.82 1,417,772.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,417,772.52