Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-155-13-17 12-0F96A4 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-5-3.0/3.7 NHPI-005-2(972) PLN-6212(16) Progress payment No. 053 Payment period ending: 05-13-19 FLATIRON WEST INC. 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,466,627.34 -23,058.40 2. a. Extra Work 2,525,228.56 32,790.49 b. Adustment Comp. -117,961.67 32,000.00 3. Materials on Hand 4. Earned Subject to Retention 46,873,894.23 41,732.09 5. Mobilization 4,340,000.00 0.00 6. Total Work Completed 51,213,894.23 7. Deductions -81,426.75 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 51,132,467.48 11,732.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,732.09