Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 15-190-14-45 12-0F96C4 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 25% Location: Federal Project: 12-ORA-5-3.7/6.2 NHPI-005-2(966) CMLN-6212(15) Progress payment No. 010 Payment period ending: 06-20-15 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,658,316.67 120,525.80 2. a. Extra Work 31,299.08 225.00 b. Adustment Comp. 36,428.36 0.00 3. Materials on Hand 366,319.16 0.00 4. Earned Subject to Retention 6,092,363.27 120,750.80 5. Mobilization 2,928,750.00 0.00 6. Total Work Completed 8,654,794.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,021,113.27 120,750.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 120,750.80