Dept. of Trans. PROGRESS Serial No. Contract No. 15-264-10-21 12-0F96C4 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 33% Location: Federal Project: 12-ORA-5-3.7/6.2 NHPI-005-2(966) CMLN-6212(15) Progress payment No. 013 Payment period ending: 09-20-15 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,748,006.62 1,247,826.25 2. a. Extra Work 122,646.18 62,446.33 b. Adustment Comp. 56,053.18 19,624.82 3. Materials on Hand 341,572.10 20,657.74 4. Earned Subject to Retention 10,268,278.08 1,350,555.14 5. Mobilization 3,709,750.00 0.00 6. Total Work Completed 13,636,455.98 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,978,028.08 1,350,555.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,350,555.14