Dept. of Trans. PROGRESS Serial No. Contract No. 15-296-09-45 12-0F96C4 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 35% Location: Federal Project: 12-ORA-5-3.7/6.2 NHPI-005-2(966) CMLN-6212(15) Progress payment No. 014 Payment period ending: 10-20-15 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,218,101.74 1,470,095.12 2. a. Extra Work 130,871.18 8,225.00 b. Adustment Comp. 56,053.18 0.00 3. Materials on Hand 269,879.00 -71,693.10 4. Earned Subject to Retention 11,674,905.10 1,406,627.02 5. Mobilization 3,709,750.00 0.00 6. Total Work Completed 15,114,776.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,384,655.10 1,406,627.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,406,627.02