Dept. of Trans. PROGRESS Serial No. Contract No. 16-145-08-04 12-0F96C4 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 50% Location: Federal Project: 12-ORA-5-3.7/6.2 NHPI-005-2(966) CMLN-6212(15) Progress payment No. 021 Payment period ending: 05-20-16 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,428,216.58 2,754,338.19 2. a. Extra Work 780,928.68 546,051.70 b. Adustment Comp. 205,488.34 28,462.00 3. Materials on Hand 122,059.00 -72,393.28 4. Earned Subject to Retention 24,536,692.60 3,256,458.61 5. Mobilization 3,905,000.00 195,250.00 6. Total Work Completed 28,319,633.60 7. Deductions -208,200.68 -138,014.71 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,233,491.92 3,313,693.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,313,693.90