Dept. of Trans. PROGRESS Serial No. Contract No. 16-173-12-32 12-0F96C4 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 53% Location: Federal Project: 12-ORA-5-3.7/6.2 NHPI-005-2(966) CMLN-6212(15) Progress payment No. 022 Payment period ending: 06-20-16 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,727,230.83 2,299,014.25 2. a. Extra Work 780,928.68 0.00 b. Adustment Comp. 205,488.34 0.00 3. Materials on Hand 42,793.00 -79,266.00 4. Earned Subject to Retention 26,756,440.85 2,219,748.25 5. Mobilization 3,905,000.00 0.00 6. Total Work Completed 30,618,647.85 7. Deductions -391,359.66 -183,158.98 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,270,081.19 2,036,589.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,036,589.27