Dept. of Trans. PROGRESS Serial No. Contract No. 16-208-10-54 12-0F96C4 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 55% Location: Federal Project: 12-ORA-5-3.7/6.2 NHPI-005-2(966) CMLN-6212(15) Progress payment No. 023 Payment period ending: 07-20-16 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,397,682.60 1,670,451.77 2. a. Extra Work 825,899.05 44,970.37 b. Adustment Comp. 226,089.34 20,601.00 3. Materials on Hand 62,906.00 20,113.00 4. Earned Subject to Retention 28,512,576.99 1,756,136.14 5. Mobilization 3,905,000.00 0.00 6. Total Work Completed 32,354,670.99 7. Deductions -430,067.64 -38,707.98 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,987,509.35 1,717,428.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,717,428.16