Dept. of Trans. PROGRESS Serial No. Contract No. 16-300-08-41 12-0F96C4 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 64% Location: Federal Project: 12-ORA-5-3.7/6.2 NHPI-005-2(966) CMLN-6212(15) Progress payment No. 026 Payment period ending: 10-20-16 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,313,273.30 1,886,188.76 2. a. Extra Work 1,141,780.92 41,451.51 b. Adustment Comp. 231,609.80 0.00 3. Materials on Hand 10,315.00 -24,524.00 4. Earned Subject to Retention 35,696,979.02 1,903,116.27 5. Mobilization 3,905,000.00 0.00 6. Total Work Completed 39,591,664.02 7. Deductions -559,677.21 -58,238.16 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 39,042,301.81 1,844,878.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,844,878.11