Dept. of Trans. PROGRESS Serial No. Contract No. 15-022-11-16 12-0F96E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 25% 12-ORA-5-6.2/8.7 Federal Project: NONE Progress payment No. 13 Payment period ending: 01-20-15 SHIMMICK CONSTRUCTION COMPANY INC 16481 SCIENTIFIC WAY IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,642,218.46 1,465,822.81 2.a. Extra Work 221,260.11 11,445.28 b. Adjustment Comp. 3. Materials on Hand 364,476.13 55,132.70 4. Earned Subject to Retention 10,227,954.70 1,532,400.79 5. Mobilization 2,755,000.00 0.00 6. Total Work Completed 12,618,478.57 7. Deductions -10,650.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,972,304.70 1,532,400.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,532,400.79