Dept. of Trans. PROGRESS Serial No. Contract No. 17-115-15-55 12-0F96E4 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 61% Location: Federal Project: 12-ORA-5-6.2/8.7 CMLN-6212(14) Progress payment No. 043 Payment period ending: 04-20-17 SHIMMICK CONSTRUCTION CO. INC 16481 SCIENTIFIC WAY IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,200,166.87 467,030.50 2. a. Extra Work 1,536,502.90 3,752.19 b. Adustment Comp. 4,712,567.62 0.00 3. Materials on Hand 512,115.54 0.00 4. Earned Subject to Retention 35,961,352.93 470,782.69 5. Mobilization 2,900,000.00 0.00 6. Total Work Completed 38,349,237.39 7. Deductions -69,757.32 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,791,595.61 470,782.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 470,782.69