Dept. of Trans. PROGRESS Serial No. Contract No. 20-325-09-05 12-0F9704 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 28% Location: Federal Project: 12-ORA-39-15.2/15.9 NONE Progress payment No. 004 Payment period ending: 11-20-20 SULLY-MILLER CONTRACTING CO 135 S STATE COLLEGE BLVD #400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 743,660.56 294,956.80 2. a. Extra Work 27,819.99 27,819.99 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 771,480.55 322,776.79 5. Mobilization 92,081.51 0.00 6. Total Work Completed 863,562.06 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 863,562.06 322,776.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 322,776.79