Dept. of Trans. PROGRESS Serial No. Contract No. 10-083-13-04 12-0G0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 18% 12-ORA-91-15.9/18.9 Federal Project: ARRA-P091(127) L-P091(127) Progress payment No. 05 Payment period ending: 03-20-10 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,519,745.16 2,905,327.52 2.a. Extra Work 25,411.31 0.00 b. Adjustment Comp. 18,399.69 0.00 3. Materials on Hand 146,161.28 59,023.07 4. Earned Subject to Retention 9,709,717.44 2,964,350.59 5. Mobilization 3,230,000.00 680,000.00 6. Total Work Completed 12,793,556.16 7. Deductions -4,260.00 -2,840.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,935,457.44 3,641,510.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,641,510.59