Dept. of Trans. PROGRESS Serial No. Contract No. 10-207-06-59 12-0G0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 34% 12-ORA-91-15.9/18.9 Federal Project: ARRA-P091(127) L-P091(127) Progress payment No. 09 Payment period ending: 07-20-10 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,460,645.50 1,967,017.59 2.a. Extra Work 149,687.23 57,258.89 b. Adjustment Comp. 210,015.61 -19,240.00 3. Materials on Hand 250,603.47 9,319.04 4. Earned Subject to Retention 22,070,951.81 2,014,355.52 5. Mobilization 3,400,000.00 0.00 6. Total Work Completed 25,220,348.34 7. Deductions -4,260.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,466,691.81 2,014,355.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,014,355.52