Dept. of Trans. PROGRESS Serial No. Contract No. 06-172-08-00 12-0G0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 42% 12-ORA-91-12.8/14.3 Federal Project: ACNH-P091(126) Progress payment No. 05 Payment period ending: 06-20-06 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 845,321.15 57,000.00 2.a. Extra Work 419.00 419.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 845,740.15 57,419.00 5. Mobilization 110,000.00 0.00 6. Total Work Completed 955,740.15 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 955,740.15 57,419.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,419.00