Dept. of Trans. PROGRESS Serial No. Contract No. 09-167-10-37 12-0G2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 59% 12-ORA-605-R0.0/R1.6 Federal Project: ACIM-X059(49) ACST-S022(22) P-S022(22) Progress payment No. 07 Payment period ending: 06-20-09 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,930,676.60 755,162.36 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -32,550.48 4. Earned Subject to Retention 3,930,676.60 722,611.88 5. Mobilization 38,000.00 0.00 6. Total Work Completed 3,968,676.60 7. Deductions -3,840.00 -300.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,964,836.60 722,311.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 722,311.88