Dept. of Trans. PROGRESS Serial No. Contract No. 06-053-12-51 12-0G2704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 18% 12-ORA-73-21.5/21.5 Federal Project: NONE Progress payment No. 10 Payment period ending: 02-20-06 P AND D LANDSCAPE MANAGEMENT SERVICES 999 TOWN AND COUNTRY DR FLOOR ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 127,073.56 7,247.45 2.a. Extra Work b. Adjustment Comp. -2,342.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 124,730.81 7,247.45 5. Mobilization 7,470.00 0.00 6. Total Work Completed 132,200.81 7. Deductions 8. a.Contract Retentions -6,236.54 -362.37 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 125,964.27 6,885.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,885.08