Dept. of Trans. PROGRESS Serial No. Contract No. 09-112-10-07 12-0G2704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 73% 12-ORA-73-21.5/21.5 Federal Project: NONE Progress payment No. 48 Payment period ending: 04-20-09 P AND D LANDSCAPE MANAGEMENT SERVICES 999 TOWN AND COUNTRY DR FLR 4 ORANGE CA 92868 Escrow No. 02222 Total Estimate This Estimate 1. Contract Itms Without Mobil. 156,156.08 690.84 2.a. Extra Work b. Adjustment Comp. -2,342.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 153,813.33 690.84 5. Mobilization 7,470.00 0.00 6. Total Work Completed 161,283.33 7. Deductions 8. a.Contract Retentions -7,690.67 -34.55 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 153,592.66 656.29 10. Reduction Amt to Escrow 11. Payment to Escrow 7,620.00 12. Net Pymt. this Estimate 656.29