Dept. of Trans. PROGRESS Serial No. Contract No. 12-115-13-37 12-0G3304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 26% 12-ORA-91-9.1/15.6 Federal Project: NONE Progress payment No. 09 Payment period ending: 04-20-12 SEMA CONSTRUCTION INC 6 ORCHARD, STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,190,895.00 3,644,841.03 2.a. Extra Work 486,300.20 129,208.28 b. Adjustment Comp. 698,817.76 0.00 3. Materials on Hand 27,734.85 27,734.85 4. Earned Subject to Retention 24,403,747.81 3,801,784.16 5. Mobilization 2,989,921.89 149,496.09 6. Total Work Completed 27,365,934.85 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,388,669.70 3,946,280.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,946,280.25