Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-13-39 12-0G3304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 45% 12-ORA-91-9.1/15.6 Federal Project: NONE Progress payment No. 15 Payment period ending: 10-20-12 SEMA CONSTRUCTION INC 6 ORCHARD, STE 150 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,440,644.28 1,770,478.13 2.a. Extra Work 1,796,177.32 148,729.76 b. Adjustment Comp. 2,301,824.97 -17,655.75 3. Materials on Hand 4. Earned Subject to Retention 42,538,646.57 1,901,552.14 5. Mobilization 2,989,921.89 0.00 6. Total Work Completed 45,528,568.46 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 45,523,568.46 1,901,552.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,901,552.14