Dept. of Trans. PROGRESS Serial No. Contract No. 13-234-14-06 12-0G3304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 69% 12-ORA-91-9.1/15.6 Federal Project: NONE Progress payment No. 27 Payment period ending: 08-20-13 SEMA CONSTRUCTION INC 320 GODDARD WAY, SUITE 150 IRVINE, CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,143,420.65 120,264.24 2.a. Extra Work 3,516,280.39 -19,958.06 b. Adjustment Comp. 3,105,164.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 49,764,865.89 100,306.18 5. Mobilization 2,989,921.89 0.00 6. Total Work Completed 52,754,787.78 7. Deductions -4,089.75 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 52,750,698.03 100,306.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,306.18