Dept. of Trans. FINAL Serial No. Contract No. 14-119-13-52 12-0G3304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-91-9.1/15.6 Federal Project: NONE Progress payment No. 33 Payment period ending: 10-30-13 SEMA CONSTRUCTION INC 320 GODDARD WAY, SUITE 150 IRVINE, CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,232,491.45 0.00 2.a. Extra Work 4,150,076.47 0.00 b. Adjustment Comp. 3,342,422.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 50,724,990.80 0.00 5. Mobilization 2,989,921.89 0.00 6. Total Work Completed 53,714,912.69 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 53,714,912.69 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00