Dept. of Trans. PROGRESS Serial No. Contract No. 10-357-08-29 12-0G7304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 10% 12-ORA-5-6.1/31.2 Federal Project: SARR-005-2(943) AE-005-2(943) Progress payment No. 05 Payment period ending: 12-20-10 ROCK BOTTOM INC 2724 LANDCO DRIVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 228,270.60 83,691.40 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 228,270.60 83,691.40 5. Mobilization 80,750.00 17,000.00 6. Total Work Completed 309,020.60 7. Deductions -3,000.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 306,020.60 97,691.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,691.40