Dept. of Trans. PROGRESS Serial No. Contract No. 08-081-13-04 12-0G7804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 87% 12-ORA-57-8.5/9.7 Federal Project: NONE Progress payment No. 03 Payment period ending: 03-20-08 T D S ENGINEERING 2899 AGOURA ROAD SUITE 171 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 346,321.80 0.00 2.a. Extra Work b. Adjustment Comp. 12,475.00 12,475.00 3. Materials on Hand 4. Earned Subject to Retention 358,796.80 12,475.00 5. Mobilization 17,000.00 0.00 6. Total Work Completed 375,796.80 7. Deductions 8. a.Contract Retentions -17,939.84 -623.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 357,856.96 11,851.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,851.25