Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 11-279-09-37 12-0G9304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 40% 12-ORA-5-5.1/5.4 Federal Project: NONE Progress payment No. 10 Payment period ending: 09-20-11 GRANSTROM CONSTRUCTION 179 NIBLICK ROAD NO 230 PASO ROBLES CA 93446 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 824,189.10 28,768.00 2.a. Extra Work 7,832.97 0.00 b. Adjustment Comp. 10,853.27 0.00 3. Materials on Hand 4. Earned Subject to Retention 842,875.34 28,768.00 5. Mobilization 85,000.00 0.00 6. Total Work Completed 927,875.34 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 927,875.34 28,768.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,768.00