Dept. of Trans. PROGRESS Serial No. Contract No. 11-206-13-30 12-0G9904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 14% 12-ORA-5-27.6/28.2 Federal Project: ACIM-052(952) Progress payment No. 04 Payment period ending: 07-20-11 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 429,290.47 219,472.56 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 49,798.14 0.00 4. Earned Subject to Retention 479,088.61 219,472.56 5. Mobilization 10,500.00 3,500.00 6. Total Work Completed 439,790.47 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 489,588.61 222,972.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 222,972.56