Dept. of Trans. PROGRESS Serial No. Contract No. 13-143-09-56 12-0G9904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 12-ORA-5-27.6/28.2 Federal Project: ACIM-052(952) Progress payment No. 25 Payment period ending: 05-20-13 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,040,130.93 -5,406.25 2.a. Extra Work 26,674.02 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,066,804.95 -5,406.25 5. Mobilization 14,000.00 0.00 6. Total Work Completed 3,080,804.95 7. Deductions 0.00 15,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,080,804.95 9,593.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,593.75