Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-208-08-34 12-0H0014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-39-5.6/5.6 Federal Project: NONE Progress payment No. 05 Payment period ending: 06-15-07 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 02258 Total Estimate This Estimate 1. Contract Itms Without Mobil. 365,338.66 0.00 2.a. Extra Work 11,907.47 7,410.25 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 377,246.13 7,410.25 5. Mobilization 40,000.00 0.00 6. Total Work Completed 417,246.13 7. Deductions 8. a.Contract Retentions -14,826.24 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 14,826.24 0.00 9. Total pay to Contractor 417,246.13 7,410.25 10. Reduction Amt to Escrow -14,820.00 0.00 11. Payment to Escrow 14,820.00 12. Net Pymt. this Estimate 7,410.25